Tesla’s giant Moss Landing Megapack battery storage project: How is it doing now?
Tesla’s Megapack farm in Moss Landing, California, has gone through quite a journey since the project was approved by the California Public Utilities Commission back in 2018. Comprised of 256 Megapacks, the 182.5 MW / 730 MWh installation would be capable of powering an estimated 136,500 homes for several hours during periods of high demand. The system is also upgradeable, with Tesla’s contract with PG&E suggesting that the battery could be ramped to 1.1 GWh in the future.
Similar to Tesla’s other high-profile energy projects, the Moss Landing Megapack farm, also known as the Elkhorn Battery Energy Storage Facility, would enhance the grid’s reliability by addressing capacity deficiencies due to increased local energy demand. It would also participate in the California Independent System Operator (CAISO) markets, providing both energy and ancillary services.
A Quick Background
It should be noted that the Megapack-powered Elkhorn Battery Energy Storage Facility is only one of four battery projects that were proposed by Pacific Gas and Electric (PG&E). Among the four, three are owned and operated by a third party — only the Tesla-powered Elkhorn Battery is owned and operated by PG&E itself. As explained by Paul Doherty, a PG&E spokesperson, the utility has two underlying contracts with Tesla regarding the facility — an Engineering, Procurement and Construction (EPC) agreement to build the battery farm, and a Long-Term Performance and Maintenance Agreement (LTPMA) that requires the EV maker to provide regular maintenance to the system for over 20 years.
The Tesla-powered Elkhorn Battery is not the largest battery among the four systems proposed by PG&E. That honor goes to the Vistra Energy Storage Facility, which features a 300 MW / 1,200 MWh Phase 1 and a 100 MW / 400 MWh Phase 2 system. Unlike the Tesla Megapack farm, which was built on a 4.5-acre plot of land in Moss Landing, the Vistra Energy Storage Facility was built into what was previously a gas-fired power plant. Utilizing over several thousand TR1300 battery racks supplied by LG Energy Solution, Vistra’s big battery was a symbol of the change happening in California’s energy sector.
Things, however, have not always been smooth sailing.

Challenges Over the Years
Being a project involving Tesla, it was no surprise that entities emerged to oppose the Elkhorn Battery project. After the Tesla-powered battery storage project was opened to public submissions about its potential environmental impacts, the California Unions for Reliable Energy took it upon themselves to stop the initiative. The union argued that Monterey County failed to meet the standards of the California Environmental Quality Act since the county should have looked further into the possibility of Tesla’s batteries overheating and exploding. The group also warned that the Tesla batteries could potentially harm the purity of the groundwater at the Moss Landing area.
These efforts proved to be in vain, however, as on February 2020, the Monterey County Planning Commission decided to approve the Tesla Megapack-powered Elkhorn Battery unanimously. Construction was set for late March, and expectations were high that it would take about one and a half years to complete. However, another speed bump for the project came in the form of the Covid-19 pandemic, which caused progress in the project to be delayed. Construction ultimately began in July 2020, and by early 2021, drone flyovers of the site showed that the Megapack installations were going smoothly.
PG&E spokesperson Doherty has informed Teslarati that as of writing, all the Tesla Megapacks have been successfully installed. The system is “currently undergoing final testing and certification, and is anticipated to be operational before Summer 2022,” pending the results of its final tests. Granted, this represents a delay from the facility’s initial targets, but PG&E’s apparent intent on being extra cautious is understandable.
An unexpected challenge for the batteries at Moss Landing came sometime last year, and while it did not involve the Tesla Megapack-powered Elkhorn Battery, it did result in energy storage projects being placed under a microscope. In early September 2021, a number of battery modules from the Phase 1 area of the Vistra Energy Storage Facility overheated, triggering the facility’s sprinkler systems. Local fire crews were sent to the site, and Vistra decided to shut down the Phase 1 zone until an investigation was completed. At this time, the Vistra Battery’s 100 MW / 400 MWh Phase 2 was just completed, so that part of the facility remained operational.
Unfortunately, the Vistra Battery’s Phase 2 area got involved in another overheating incident in February 2022. Similar to the incident in September 2021, the batteries in the Vistra facility’s Phase 2 area triggered a fire alarm. The local fire department attended to the facility once more, where they found roughly ten battery racks that were melted. This incident, which happened within five months since the September 2021 issue, caused the reactivation efforts for the Phase 1 area to be paused and Phase 2 to be shut down. This meant that the Vistra battery, at least until investigations are completed for both incidents, will likely remain offline.

PG&E’s Tesla Megapack Management System
What is rather interesting about the Elkhorn Battery Energy Storage Facility is the fact that while it features Tesla’s flagship battery storage units, the Megapack batteries themselves would not be managed by software from the electric vehicle maker. Instead of Tesla’s Autobidder platform, PG&E has opted to utilize “Fluence’s AI-powered Trading Platform to provide optimization and market bidding services,” confirmed Doherty.
Tesla’s Autobidder platform has been successfully operating at the Hornsdale Power Reserve (HPR) in South Australia, where it has effectively added competition to drive down energy prices in the area. But inasmuch as Autobidder is designed to work seamlessly with products like the Megapack, Fluence’s Trading Platform is pretty powerful and capable on its own. Seyed Madaeni, the chief digital officer of Fluence, expressed his optimism for the company’s AI-powered solution and its use in the Tesla-powered Elkhorn Battery Energy Storage Facility.
“PG&E was one of the first utilities to appreciate the need for a sophisticated AI-enabled bidding technology to optimize its energy storage assets. This technology-agnostic software provides PG&E with a single tool that can optimize not only the Moss Landing project, but potentially entire portfolios of generation and storage resources to enhance affordability of resources. We are excited to work with PG&E to use advanced technology to improve the efficiency and reliability of the CAISO market and lower costs for California consumers,” Madaeni said.
Future Expansions
While the Moss Landing batteries have faced their own fair share of challenges, PG&E remains extremely optimistic about energy storage as a whole. Depending on the success of the Tesla Megapack-powered Elkhorn Battery, the system could be expanded even further to 1.1 GWh. All signs seem to be pointing to this scenario, especially considering the state’s intense focus on sustainability. Interestingly enough, Tesla’s Megapacks courted some controversy themselves last year when one unit in the Victoria Big Battery in Australia caught fire during tests. The incident ultimately damaged two Megapack units, and it incited a lot of skepticism over the potential dangers of battery storage technology.
If PG&E’s massive Tesla Megapack farm could prove itself as reliable as the now-iconic Powerpack-powered Hornsdale Power Reserve in South Australia, then the project could potentially accelerate the adoption of battery storage systems in the near future. PG&E definitely seems to be confident about the potential of battery storage solutions, with the utility moving forward with Vistra on plans to expand the Vistra Battery even further.
Vistra spokesperson Meranda Cohn has stated that the incidents from September 2021 and February 2022 would not impact the companies’ push to move forward with its battery project. PG&E spokesperson Doherty was on the same page, telling the Monterey County Weekly that he has “full confidence” in the project and that an analysis of the incidents in September 2021 and February 222 revealed that the batteries were actually not at fault. The PG&E spokesperson further noted that the utility is committed to “advancing the field of fire safety at battery storage facilities,” which could be highlighted by the fact that it was awarded for its fire safety work at its Tesla-powered Elkhorn Battery Energy Storage Facility.
Don’t hesitate to contact us with news tips. Just send a message to simon@teslarati.com to give us a heads up.
Energy
Tesla Energy had a blockbuster 2024

Tesla Energy has become the undisputed dark horse of the electric vehicle maker. This was highlighted by Tesla Energy’s growing role in the company’s overall operations in the past quarters.
And as per Tesla’s year-end milestone posts on X, Tesla Energy had a blockbuster 2024.
Tesla Energy’s 2024 milestones:
- As per Tesla on its official social media account on X, the company has hit over 800,000 Powerwalls installed worldwide.
- From this number, over 100,000 Powerwall batteries have been enrolled in virtual power plant (VPP) programs.
- The Powerwall 3 has officially been launched in the United States, Canada, Puerto Rico, the U.K., Germany, Italy, Australia, and New Zealand.
- The Tesla Megapack hit over 22 GWh in operation across more than 60 countries across the globe.
- The Lathrop Megafactory, which produces the Megapack, has been ramped to 40 GWh per year.
- The Lathrop Megafactory has also produced its 10,000th Megapack battery.
- The Shanghai Megafactory was completed in just seven months, and it is ready to start Megapack production in Q1 2025.
Hit 800k Powerwalls installed worldwide
— Tesla (@Tesla) December 31, 2024
Also:
– Over 100k Powerwalls are now enrolled in VPP programs
– Launched Powerwall 3 in the US, Canada, Puerto Rico, UK, Germany, Italy, Australia & New Zealand
– Megapack hit 22+ GWh in operation across 60+ countries
– Ramped… pic.twitter.com/bE88DpeyTg
Powerwall owners’ 2024 impact:
- As per Tesla Energy, Powerwall owners generated a total of 4.5 TWh of solar energy globally in 2024. This was equivalent to powering a Model 3 for more than 17 billion miles.
- A total of 1.1 TWh of energy was stored in Powerwalls in 2024. This protected homes from over 5.8 million outages during the year.
- Tesla’s Storm Watch feature for Powerwall batteries covered 2.8 million severe weather events over the year.
- Powerwall owners saw collective savings of over $800 million on utility bills.
- Virtual Power Plants contributed over 2.2 GWh of power to the grid. This reduced the need for 2,200 metric tons of fossil fuel peaker plant emissions.


Don’t hesitate to contact us with news tips. Just send a message to simon@teslarati.com to give us a heads up.
Energy
Utah’s rPlus Energies breaks ground on Tesla Megapack battery system

Utah-based rPlus Energies recently held the groundbreaking ceremony for the Green River Energy Center, a 400 MW solar PV and 400 MW/1,600 MWh battery storage project in Eastern Utah. Tesla Megapacks will be used as the upcoming facility’s battery storage solution.
At 400 MW/1,600 MWh, the Green River Energy Center is expected to become one of the largest solar-plus-storage projects under development in the United States. Once operational, the facility would supply power to PacifiCorp under a power purchase agreement, as noted in a press release.
Utah Gov. Spencer Cox shared his excitement for the project during the Green River Energy Center’s groundbreaking event. As per the Utah Governor, the solar and battery storage system represents a notable step forward for the state’s sustainable energy efforts.
NEWS: rPlus Energy has just broken ground on a new $362 million @Tesla Megapack battery energy storage system in Utah.
— Sawyer Merritt (@SawyerMerritt) September 24, 2024
This 400 MW solar PV and 400 MW/1,600 MWh battery storage project is one of the largest solar-plus-storage projects under construction in the nation. The entire… pic.twitter.com/ubPOUnPWEf
“This project is being built in rural Utah, by rural Utahns, and for all of Utah. When rural Utah thrives, the entire state prospers. Today, we’re not just breaking ground—we’re building a future of affordable, abundant energy in Utah,” the official noted.
The Green River Energy Center secured over $1 billion in construction debt financing earlier this year. The facility is also expected to create about 500 jobs, many of which will be filled by local workers. With this in mind, the solar and battery farm would likely prove to be a boost to Emery County’s economy, enhancing tax revenue, strengthening public services, and offering long-term employment opportunities for the area’s residents.
Sundt Construction will serve as the project’s contractor, EliTe Solar will supply the solar modules, and Tesla will provide the battery storage system for the project. Luigi Resta, President and CEO of rPlus Energies, noted that the Green River Energy Center is special because of the entities that have worked together to make the facility a reality.
“It’s the partners that make this project special, that have made this monumental project possible. From our equipment providers to the onsite talent, and the support of the local and regional community, we owe this project’s success to each of you,” he stated.
Don’t hesitate to contact us with news tips. Just send a message to simon@teslarati.com to give us a heads up.
Energy
Tesla Energy loses director who brought Autobidder

Tesla Energy is losing a director who brought Autobidder, a real-time trading and control platform that provides value-based asset management and portfolio optimization, to the company.
Rohan Ma, who has been at Tesla for just under eight years, announced he would depart the company on LinkedIn, aiming to take on a new opportunity elsewhere.
Ma posted:
“After eight years at Tesla, this will be my last week. It was a ride of a lifetime! Today, Tesla Energy is thriving and I can confidently say it’s in the best position it has ever been in to drive impact toward the original mission I signed up for. I’m proud to have contributed over the years to where it is now, and will be cheering the team on from the sidelines as they carry the torch forward and continue to relentlessly solve problems at the frontier of the energy transition.”
Ma started as the Senior Manager of Energy Optimization at Tesla back in November 2016. After four-and-a-half years at the position, he then moved on to a new role as the Director of Energy and Software Optimization. He has been in that role for over three years.
The exit of Ma is the latest in Tesla’s tough year in terms of losing high-level employees.
Earlier this year, as a part of widespread layoffs, Tesla eliminated up to 20 percent of its workforce and people like Rebecca Tinucci, who was the company’s Senior Director of EV Charging.
Tesla also lost Rohan Patel, Vice President of Global Public Policy and Business Development, and Martin Viecha, who was Head of Investor Relations, are just a few notables to depart.
Autobidder
Tesla’s Autobidder platform helps owners and operators make money by autonomously monetizing battery assets. It is a real-time trading and control platform that maximizes revenue according to business objectives and risk preferences.
Tesla Megapack, Autobidder to be deployed in big battery project in Queensland
Autobidder already has hundreds of megawatt-hours under management and continues to scale. It is hosted on Tesla’s secure cloud infrastructure that is engineered to handle large and complex computations.
Without Ma’s expertise, Autobidder would likely not be involved in Tesla’s Energy division at all, and although it is not frequently discussed, it is still a major part of the business’s growth over the past several years.
I’d love to hear from you! If you have any comments, concerns, or questions, please email me at joey@teslarati.com. You can also reach me on Twitter @KlenderJoey, or if you have news tips, you can email us at tips@teslarati.com.