Tesla formally wins final environmental approval to open Gigafactory Berlin

Credit: @Gf4Tesla/Twitter

Published

on

The wait is finally over. After a long process that saw delays, controversies, and other drama, Tesla Gigafactory Berlin has won its final environmental approval from Germany. An official document confirming the update was published by the State of Brandenburg, outlining the next steps that the electric vehicle maker needs to do to start vehicle production in its Germany-based electric vehicle factory. 

As per the state’s press release, the approval for Giga Berlin covers several activities, such as the production of up to 500,000 vehicles per year. The approval also includes battery cell production activities within the Giga Berlin complex, which should allow Tesla to manufacture its in-house cells from within Germany. 

“The project, which was approved with the 536-page decision, includes the plant for the production of up to 500,000 vehicles per year, aluminum smelting plants and an aluminum foundry, plants for surface treatment, heat generation, and storage. The facility also includes battery cell production, an operational wastewater treatment plant, a fire brigade equipment house, a high-bay warehouse, as well as laboratories and workshops,” the press release read. 

Giga Berlin’s new graffiti panels as of early FebruGiga Berlin’s new graffiti panels as of early February 2022. (Credit: @Gf4Tesla/Twitter)ary 2022. (Credit: @Gf4Tesla/Twitter)

It should be noted that while it may have taken two years to get to this point, Gigafactory Berlin’s formal approval was still completed in a quick manner, at least relatively speaking. The past two years, after all, required the State Office of the Environment to not only inspect and approve the factory itself, but also the entire industrial area with several large-scale facilities. Environment Minister Alex Vogel expressed his thanks to the state’s employees and other authorities for Giga Berlin’s quick approval process.

“As a high-performing state administration, you have always focused on the technical requirements, the high level of protection of the environment, the protection of the general public and the neighborhood from dangers, even under the pressure of great public interest and unreasonable harassment as well as the legal certainty of the procedure. In times of climate crisis, the availability of water will play an increasingly important role for future developments and settlements. Above all, digitization can help to simplify and accelerate processes without restricting environmental standards and participation rights,” Vogel said. 

District Administrator Rolf Lindemann emphasized that Giga Berlin benefits the region. The fact that the project faced much adversity, and was still able to achieve a milestone such as a final environmental approval in a relatively short time, proves that the project’s potential is vast. He also noted that Giga Berlin, as well as those that have been working with Tesla over the past two years to approve the project, shall face whatever challenges lie ahead with vigor.  

“The Oder-Spree district described the Tesla Gigafactory as a real stroke of luck for the development of our region. We have therefore mobilized all our strength to help turn this unique opportunity into a visible success. It wasn’t always easy, and we’re anything but done when it comes to the final form of the overall project. But we all have reason to be proud of what we have achieved so far, despite all prophecies of doom.

“That is why we will face the further challenges that lie ahead with confidence and with undiminished vigor. I am referring to the official support of the further expansion stages, the completion of the battery factory and of great importance, especially for local politics: as far as possible, a stress-free integration of the Gigafactory into the traffic infrastructure . However, in order to be able to meet the sustainability aspect and smooth mobility in connection with production, it is of course necessary to start building housing close to the location and to create the associated social infrastructure. We trust in the same support from the state government that we have been able to rely on in the past,” Lindemann said. 

A look inside Tesla Giga Berlin’s body shop for the Model Y. (Credit: Tesla Inc.)

While Giga Berlin’s final environment approval has been secured, Tesla still has to ensure that it meets the state’s requirements. These are highlighted by the mammoth size of its approval documents, which comprise over 23,700 pages in 66 files. More than 400 ancillary provisions are included, involving topics such as requirements for groundwater protection as well as water-saving and wastewater-reducing measures, species protection measures, limit values for air pollutants and regulations on their measurement as well as occupational safety requirements. Other specific rules on the plant’s operations, particularly with regards to how it affects the area’s groundwater, were also highlighted in the press release. 

“There are 113 air pollution control requirements, which include respective chimney heights for each exhaust air stream. In addition, 22 requirements determine the methods and intervals at which the exhaust air is to be measured. 96 requirements for drinking water protection, waste water disposal and rainwater specify, among other things, limit values for discharge into the waste water pressure line and corresponding cleaning processes. When using building materials, it is important to ensure that no harmful substances get into the groundwater. With groundwater monitoring, both the formation of new groundwater and the quality of the groundwater must be checked regularly. In view of the tense water situation, not least due to climate change, it should be possible to react to changes as early as possible.

“After the inspection by the approval authority, the entire system falls under the provisions of the Hazardous Incidents Ordinance (12th BImSchV) and must therefore take special precautions to prevent incidents and limit the effects of incidents, as well as maintain an appropriate safety distance from adjacent protected objects. Tesla must draw up an incident concept and comply with special information obligations,” the press release read. 

The state noted that Tesla may now start or continue with the further construction of Giga Berlin and that objections to the project now have “no suspensive effect.” It should be noted, however, that before Tesla can actually put its Model Y production facility into operation, several ancillary provisions must be met first. These provisions, which include the installation of measuring devices for air pollutants and precautions for fire protection and accidents, will be checked by the responsible authorities. Once Tesla completes this step, Model Y production for customer vehicles could finally commence. 

Needless to say, all eyes are now focused on how quickly Tesla can meet the requirements for Giga Berlin’s operational permit. 

Don’t hesitate to contact us with news tips. Just send a message to simon@teslarati.com to give us a heads up.

Simon is a reporter with a passion for electric cars and clean energy. Fascinated by the world envisioned by Elon Musk, he hopes to make it to Mars (at least as a tourist) someday.

News

Armored Tesla Cybertruck “War Machine” debuts at Defense Expo 2025

Lorem ipsum dolor sit amet, consectetur adipisicing elit, sed do eiusmod tempor incididunt ut labore et dolore magna aliqua.

Published

on

Photo: Unplugged Performance

Temporibus autem quibusdam et aut officiis debitis aut rerum necessitatibus saepe eveniet ut et voluptates repudiandae sint et molestiae non recusandae. Itaque earum rerum hic tenetur a sapiente delectus, ut aut reiciendis voluptatibus maiores alias consequatur aut perferendis doloribus asperiores repellat.

Lorem ipsum dolor sit amet, consectetur adipisicing elit, sed do eiusmod tempor incididunt ut labore et dolore magna aliqua. Ut enim ad minim veniam, quis nostrud exercitation ullamco laboris nisi ut aliquip ex ea commodo consequat.

“Duis aute irure dolor in reprehenderit in voluptate velit esse cillum dolore eu fugiat”

Nemo enim ipsam voluptatem quia voluptas sit aspernatur aut odit aut fugit, sed quia consequuntur magni dolores eos qui ratione voluptatem sequi nesciunt.

Et harum quidem rerum facilis est et expedita distinctio. Nam libero tempore, cum soluta nobis est eligendi optio cumque nihil impedit quo minus id quod maxime placeat facere possimus, omnis voluptas assumenda est, omnis dolor repellendus.

Nulla pariatur. Excepteur sint occaecat cupidatat non proident, sunt in culpa qui officia deserunt mollit anim id est laborum.

Sed ut perspiciatis unde omnis iste natus error sit voluptatem accusantium doloremque laudantium, totam rem aperiam, eaque ipsa quae ab illo inventore veritatis et quasi architecto beatae vitae dicta sunt explicabo.

Neque porro quisquam est, qui dolorem ipsum quia dolor sit amet, consectetur, adipisci velit, sed quia non numquam eius modi tempora incidunt ut labore et dolore magnam aliquam quaerat voluptatem. Ut enim ad minima veniam, quis nostrum exercitationem ullam corporis suscipit laboriosam, nisi ut aliquid ex ea commodi consequatur.

At vero eos et accusamus et iusto odio dignissimos ducimus qui blanditiis praesentium voluptatum deleniti atque corrupti quos dolores et quas molestias excepturi sint occaecati cupiditate non provident, similique sunt in culpa qui officia deserunt mollitia animi, id est laborum et dolorum fuga.

Quis autem vel eum iure reprehenderit qui in ea voluptate velit esse quam nihil molestiae consequatur, vel illum qui dolorem eum fugiat quo voluptas nulla pariatur.

Continue Reading

News

Tesla Megapacks chosen for 548 MWh energy storage project in Japan

Tesla plans to supply over 100 Megapack units to support a large stationary storage project in Japan, making it one of the country’s largest energy storage facilities.

Published

on

Tesla-megapack-pilot-project-willowbrook-mall
Credit: Tesla

Tesla’s Megapack grid-scale batteries have been selected to back an energy storage project in Japan, coming as the latest of the company’s continued deployment of the hardware.

As detailed in a report from Nikkei this week, Tesla plans to supply 142 Megapack units to support a 548 MWh storage project in Japan, set to become one of the country’s largest energy storage facilities. The project is being overseen by financial firm Orix, and it will be located at a facility Maibara in central Japan’s Shiga prefecture, and it aims to come online in early 2027.

The deal is just the latest of several Megapack deployments over the past few years, as the company continues to ramp production of the units. Tesla currently produces the Megapack at a facility in Lathrop, California, though the company also recently completed construction on its second so-called “Megafactory” in Shanghai China and is expected to begin production in the coming weeks.

READ MORE ON TESLA MEGAPACKS: Tesla Megapacks help power battery supplier Panasonic’s Kyoto test site

Tesla’s production of the Megapack has been ramping up at the Lathrop facility since initially opening in 2022, and both this site and the Shanghai Megafactory are aiming to eventually reach a volume production of 10,000 Megapack units per year. The company surpassed its 10,000th Megapack unit produced at Lathrop in November.

During Tesla’s Q4 earnings call last week, CEO Elon Musk also said that the company is looking to construct a third Megafactory, though he did not disclose where.

Last year, Tesla Energy also had record deployments of its Megapack and Powerwall home batteries with a total of 31.4 GWh of energy products deployed for a 114-percent increase from 2023.

Other recently deployed or announced Megapack projects include a massive 600 MW/1,600 MWh facility in Melbourne, a 75 MW/300 MWh energy storage site in Belgium, and a 228 MW/912 MWh storage project in Chile, along with many others still.

What are your thoughts? Let me know at zach@teslarati.com, find me on X at @zacharyvisconti, or send us tips at tips@teslarati.com.

Tesla highlights the Megapack site replacing Hawaii’s last coal plant

Need accessories for your Tesla? Check out the Teslarati Marketplace:

Continue Reading

News

Elon Musk responds to Ontario canceling $100M Starlink deal amid tariff drama

Ontario Premier Doug Ford said, opens new tab on February 3 that he was “ripping up” his province’s CA$100 million agreement with Starlink in response to the U.S. imposing tariffs on Canadian goods.

Published

on

NORAD and USNORTHCOM Public Affairs, Public domain, via Wikimedia Commons

Elon Musk company SpaceX is set to lose a $100 million deal with the Canadian province of Ontario following a response to the Trump administration’s decision to apply 25 percent tariffs to the country.

Starlink, a satellite-based internet service launched by the Musk entity SpaceX, will lose a $100 million deal it had with Ontario, Premier Doug Ford announced today.

Ford said on X today that Ontario is banning American companies from provincial contracts:

“We’ll be ripping up the province’s contract with Starlink. Ontario won’t do business with people hellbent on destroying our economy. Canada didn’t start this fight with the U.S., but you better believe we’re ready to win it.”

It is a blow to the citizens of the province more than anything, as the Starlink internet constellation has provided people in rural areas across the globe stable and reliable access for several years.

Musk responded in simple terms, stating, “Oh well.”

It seems Musk is less than enthused about the fact that Starlink is being eliminated from the province, but it does not seem like all that big of a blow either.

As previously mentioned, this impacts citizens more than Starlink itself, which has established itself as a main player in reliable internet access. Starlink has signed several contracts with various airlines and maritime companies.

It is also expanding to new territories across the globe on an almost daily basis.

With Mexico already working to avoid the tariff situation with the United States, it will be interesting to see if Canada does the same.

The two have shared a pleasant relationship, but President Trump is putting his foot down in terms of what comes across the border, which could impact Americans in the short term.

Continue Reading